By Keith Mobley
Overall equipment effectiveness (OEE) can be an accurate representation of overall plant performance. Derived from Total Productive Maintenance (TPM) and the Toyota Production System (Lean), OEE is a single, calculated value that represents the plant’s effectiveness in three key performance indicators:
- Availability or runtime
- Production rate
- Quality rate
This straightforward value was intended to be the product of these three values, but has become a convoluted, almost infinite variation of calculations.
Why does OEE matter for a successful organization?
OEE is more than just a metric—it is a strategic tool that helps organizations identify inefficiencies and prioritize improvement efforts. By measuring availability, performance, and quality in a single value, OEE provides a clear picture of how effectively equipment and processes are utilized. A high OEE score indicates that assets are running at their full potential, minimizing downtime, reducing waste, and maximizing output. This translates directly into lower operating costs, improved customer satisfaction, and greater competitiveness in the market. Conversely, a low OEE score highlights areas for improvement, enabling leaders to make data-driven decisions that drive operational excellence.
The Correct Calculation for OEE
The correct calculation for OEE is the product of the availability, production, and quality rates and should be calculated as follows:
OEE = Availability Rate × Production Rate × Quality Rate
Availability Rate:
Availability rate is the actual production runtime for a specific time interval divided by the “planned” runtime for the same interval. For example, an asset that is planned and scheduled to operation eight (8) hours per day, five (5) days per week has a total availability of forty (40) hours. If it has an actual runtime of twenty (20) hours, the resultant Availability Rate is fifty (50%) percent.
Production Rate:
Production rate is the actual gross units produced for a specific time interval divided by the number of units that should have been produced. Technically, the denominator in this case should be the ideal rate as defined by the asset’s design specifications, but in most cases assets are operating well above the original “nameplate” production rate. Therefore, the best demonstrated production rate should be used for this calculation. Best demonstrated is simply the best sustainable rate, based on asset history that your plant has been able to achieve.For example, when an asset produces 1,000 units per hour and its best demonstrated rate is 2,000 units per hour, the resultant Production Rate is 50%.
Quality Rate:
Quality rate should be straightforward. It is the total quality units produced divided by the total or gross units produced. Total quality units is defined as the total (gross) units produced minus all scrap, rejects, reworks and any other units that cannot be sold as prime. For example, if the asset produces 1,000 total units but 100 units are rejected, the numerator becomes 900 and the denominator is 1,000 or a Quality Rate of 90%.
Once these three values are determined, the final OEE calculation is simply the product of the three values, expressed as percentages, or 50% x 50% x 90% or 22.5%.